SERVICE SECTORS

Transportation

PROJECT: SEPTA Regional Rail Bridges 5.03/5.03A
over Wayne Avenue

Featured Transportation-Bridges Projects

Project Challenge:

The Southeastern Pennsylvania Transportation Authority (SEPTA) concluded that Bridges 5.03 and 5.03A located within the Main Line portion of its Regional Rail system were in need of major repair or replacement. The bridges carry daily commuter trains from six of the seven Regional Rail lines over Wayne Avenue. The location of Bridge 5.03 made it virtually inaccessible to perform major repair of replacement. The bridge is located at the south end of SEPTA's Wayne Junction Station and was built inbetween Main Line Bridge 5.03A and Chestnut Hill East Line Bridge 5.04. Bridge 5.03 is one on the heaviest traveled bridges in SEPTA's entire system and could only be taken out of service during short construction windows. SEPTA retained Klein and Hoffman, Inc. (K&H) to lead a multidisciplinary team to provide professional engineering services for
replacement of Bridge 5.03 and repair of adjacent Bridge 5.03A from the investigation phase through design and construction.

Project Solution:

Existing conditions were evaluated, load rating analyses performed, and alternative programs for rehabilitation or replacement were developed. Alternative analysis included constructability analysis, construction phasing and construction cost estimates that allowed SEPTA to determine whether each structure needed to be replaced or rehabilitated.

Once it was determined that Bridge 5.03 required full replacement of the superstructure, maintaining rail service during construction became the top priority. K&H developed an innovative strategy to replace Bridge 5.03 in halves. The east half of the bridge carried outbound rail traffic and nearby track interlockings allowed for its replacement utilizing conventional construction during an 8-week track outage while outbound rail traffic was diverted across adjacent Bridge 5.03A.

The west side of the bridge carried inbound rail traffic and the existing interlockings did not allow for diversion of rail traffic across Bridge 5.03A. Consequently, the west half of the bridge was replaced using "roll-in" construction techniques. The new superstructure was constructed on a temporary runway structure adjacent to the west half of Bridge 5.03 while the rail line remained in service. Once the preparatory work was complete,
a single 52-hour weekend track outage was used to demolish the existing superstructure, roll and lower the new superstructure into place, and restore the inbound track to service.

Repair of Bridge 5.03A was more straightforward. K&H engineered reinforcement to strengthen the girders and designed a replacement deck structure. In order to rehabilitate the bridge, rail traffic was diverted onto the newly constructed Bridge 5.03 with no interruption to revenue service.

CLIENT/OWNER: Southeastern Pennsylvania
    Transportation Authority (SEPTA)












 

More Transportation Projects



HOME | ABOUT US | LIBRARY | CAREERS | LINKS | CONTACT US

SERVICE SECTORS:
Building Envelope | Façade Ordinance | Façade Restoration | Curtainwall/Window
Roof Asset Management | Historic Preservation | Assessment and Resource Planning
New Structures | Structural Rehabilitation and Adaptive Reuse
Civil/Environmental | Transportation | Marine/Waterfront

WEB ACCESS SERVICES


© 1999-2010 Klein and Hoffman, Inc. All Rights Reserved.