|
|
 |
SERVICE SECTORS
Transportation
PROJECT: SEPTA - Broad Street
Subway Stations
Girard, Spring Garden, and Walnut-Locust
|
Featured Transportation-Passenger Station Projects
|
 |
Project Challenge:
Continuing in its efforts to renovate the aging passenger stations
along the Broad Street Subway Line, the Southeastern Pennsylvania
Transportation Authority (SEPTA) retained Klein and Hoffman,
Inc. (K&H) to lead a multi-firm team to design renovations
and improvements for the Walnut-Locust, Girard and Spring Garden
subway stations. The stations were constructed in the early
1900's and the underground passenger platforms can only be accessed
using the original stairway systems. The project's main objective
was to install new elevators, reconstruct the original stairways,
and to implement all other modifications necessary to provide
a fully compliant ADA accessible path from the street level
down to each platform. As an additional goal, SEPTA directed
the design team to transform the out-dated stations into clean
and functional facilities using durable, low maintenance, vandal-resistant
materials.
Project Solution:
The K&H team worked closely with SEPTA to determine viable
locations for the new passenger elevators. Each potential location
was evaluated with regard to the need for easements and property
acquisition; compliance with ADA and regulatory requirements;
the need for utility relocation within the stations and streets;
the constructability of proposed framing modifications; support
for the new elevators; the impact on maintaining uninterrupted
operation of the station; and the impact on construction cost
and schedule.
Based on the results of the evaluation, site-specific elevator
locations were selected for each station. The stations each
have a concourse level above the platform level and separate
street-to-concourse and concourse-to-platform elevators were
required to accommodate the various station configurations.
In addition to the new elevators, project components included
new head houses and streetscape design; stair rehabilitation
and replacement; installation of tactile warning strips along
the platform edges; new floor, ceiling, wall and column finishes;
structural restoration and water infiltration mitigation; new
passenger amenities; signage and lighting improvements; and
artistic elements to comply with SEPTA's Percent for Art Program.
As Prime Consultant, K&H's responsibilities included overall
project management, quality assurance and control, conceptual
station planning, regulatory compliance and approvals, technical
oversight of team members, structural and restoration engineering
and design, water infiltration mitigation. Construction documentation
was prepared as two separate bid packages, one for Walnut-Locust
Station and a second package for Girard and Spring Garden Stations.
Walnut-Locust construction will be completed in 2008 and construction
for Girard and Spring Garden Stations is anticipated to begin
in 2009.
CLIENT/OWNER: Southeastern Pennsylvania
Transportation Authority (SEPTA)
|

|
|
|
|
|
|
|
| |
More Transportation Projects
|
 |
1 2 3 4 5 6 << previous next >>
|
|
|
|
|
|
HOME | ABOUT
US | LIBRARY | CAREERS
| LINKS | CONTACT US
SERVICE SECTORS:
Building Envelope | Façade
Ordinance | Façade Restoration |
Curtainwall/Window
Roof Asset Management | Historic
Preservation | Assessment and Resource
Planning
New Structures | Structural
Rehabilitation and Adaptive Reuse
Civil/Environmental | Transportation
| Marine/Waterfront
WEB ACCESS SERVICES
© 1999-2010 Klein and Hoffman, Inc. All Rights Reserved.
|
|