SERVICE SECTORS

Civil/Environmental

PROJECT: Richmond Wastewater Treatment Plant
Effluent Treatment Facilities

Featured Civil/Environmental Projects

Project Challenge:

For over 25 years, Klein and Hoffman (K&H) has provided structural design and construction support services for major
additions and improvements to the Richmond Wastewater Treatment Plant. The Effluent Treatment Facilities are located in the flood plane with 100 year flood level at about 18 feet above the grade. Construction of these facilities included a 100 ft wide x 150 ft long x 70 ft deep reinforced concrete filter building structure about 20 feet below and 50 feet above grade. Blower, electrical and process control rooms were constructed over effluent, influent conduits and wet well areas. This building was connected to eighteen effluent filter tanks, a filter pipe gallery and an access building, having an expansion joint between the two structures. The structures were supported over steel H-Piles and tie down rock anchors.

Project Solution:

The concrete mat foundations were supported over 50-ton steel H-Piles bearing on rock, and were held by 50 ton capacity rock anchors to resist uplift due to hydrostatic head of 40 feet. During pile driving operations, it was discovered that some of the piles were going out-of-plumb while others had bent. Because of the varying rock elevations, pile tips were getting damaged while going through the soil and then suddenly hitting the hard rock. Protective shoes with cutting teeth were added at all the piles tips to solve the problem.

During installation of the uplift rock anchors, in some areas, the augercast holes (for No. 18 size threaded steel reinforcing bars) kept caving in and were getting filled up with water and debris. This was due to the highly weathered rock conditions encountered in those areas. Large diameter casings were used to keep the holes clean for grouting the annulat space between the sheathing for the anchor and the casing. At areas, where the top of the rock was just a few feet below the bottom of the mat foundation, the steel piles could not be driven and had to be replaced by specially designed concrete posts.

OWNER: City of Richmond Department of
    Public Utilities
CLIENT: Greeley and Hansen, LLC





 
 

More Civil/Environmental Projects



HOME | ABOUT US | LIBRARY | CAREERS | LINKS | CONTACT US

SERVICE SECTORS:
Building Envelope | Façade Ordinance | Façade Restoration | Curtainwall/Window
Roof Asset Management | Historic Preservation | Assessment and Resource Planning
New Structures | Structural Rehabilitation and Adaptive Reuse
Civil/Environmental | Transportation | Marine/Waterfront

WEB ACCESS SERVICES


© 1999-2008 Klein and Hoffman, Inc. All Rights Reserved.